Construction Progress Update – K Residence April 2025.

Construction works on our K Residence are progressing according to plan, and we are pleased to share the latest updates:

  • Water installation has been completed throughout the building
  • Electrical installation has also been completed
  • Thermal insulation of the building is finished
  • Interior plastering is fully completed
  • Anodized aluminum joinery has been installed, except on the commercial premises


Currently ongoing works include:

  • Tiling on the 10th floor
  • Final works on the roof are in progress
  • Wall smoothing (gletovanje) is being finalized on the 6th floor
  • Entrance doors are being installed on the 9th floor


The following works have been completed on floors 1, 2, and 3:

  • Wall painting
  • Installation of circuit breakers and sockets
  • Ready for parquet flooring installation


Façade works are advancing steadily:

  • Approximately 80% of the building has been covered with thermal insulation (styrofoam)
  • Doweling and preparation for the final façade layer are underway


On the 4th floor:

  • Air conditioning units have been installed
  • Terrace safety elements are currently being installed


We will continue to provide regular updates as we move forward. Thank you for your trust!

09.04.2025.