We are pleased to provide you with an update on the construction progress of the K Eden project throughout September. During the past period, several key construction phases were successfully completed, marking signicant progress in the development of the project.
- Excavation works for garage levels -2 and -1 have been completed.
- Construction of the foundation slab has been completed.
- The industrial flooring works in the garage levels have been completed.
The works are progressing according to the planned schedule, in compliance with the applicable technical standards and quality requirements.
In the upcoming period, we will continue with the planned construction phases and keep you regularly informed about the further progress of the project.
Thank you for your trust.