This month, we are sharing the latest progress on the K Residence project. The transformation of our building continues, and we are pleased to inform you about the activities currently underway:
- The installation of metalwork on the first floor is in progress, as well as insulation work on the terraces and in the bathrooms.
- Plastering has been completed on the first and third floors, and the second floor is currently being plastered.
- Electrical, water, and air conditioning installations are being carried out on the fifth floor.
- Masonry work has been completed on the first six floors, and the construction of the seventh floor is underway.
The work is progressing according to plan, and our team is diligently attending to every detail to ensure quality and your future comfort.