Work on our building is progressing according to plan, and we are approaching the final stages!
- The outdoor air conditioning units have been installed, while the indoor units are currently being mounted on the upper floors.
- Doors have already been installed on six floors, and in the coming days they will also be completed on the 7th, 8th, 8. and 9th floors.
- Parquet flooring has been fully installed on the 8th floor, while installation on the 9th floor will begin shortly.
- Sanitary fixtures are being finalized on the 7th floor.
- Painting is nearing completion on the 10th floor, while the 11th floor has entered the plastering phase.
- The exterior façade of the building has been completed, and scaffolding will be removed in the coming days, giving the building its final appearance. The scaffolding will then be moved to the interior side facing the square.
- Rail holders have been installed on the 7th floor, while glass panels have been mounted on the 4th floor. Staircase railings have also been installed.
- In addition, the cladding for external air conditioning units has been completed in the areas where the façade is finished.
Another wave of progress is here, with the final details giving the building an increasingly distinctive and modern look.