Work Progress at K Residence construction site – February 2025.

Welcome to another monthly progress review of the construction work at K Residence. We are making steady progress toward achieving our project goals, and every day brings us one step closer to your new home.

– Water installation is being completed on the 11th floor

– Styrofoam for the façade has been installed up to the 10th floor

– Metalwork installation is in progress on the 10th floor

– Plastering is underway on the 10th floor

– Drywall work and preparation for insulation before tiling are in progress on the 8th floor

– Tiling is currently being installed on the 7th floor

– Smoothing of the first four floors is complete – painting will begin soon

We are progressing as planned and getting closer to completion!


13.02.2025.