Work Progress at K Residence construction site – September 2024.

This September, the progress of work at our K Residence construction site is in full swing. All phases of the work are advancing successfully and rapidly, bringing us closer to our goal within the anticipated deadlines.

– The slab for the tenth floor has been poured, meaning only the concreting of the final floor remains;

-The masonry work on the eighth floor is being completed, while half of the ninth floor has already been bricked up;

-The air conditioning installation on the seventh floor is finished, and plumbing work is underway on the same floor;

-Electrical installation work is being carried out on the sixth floor;

-The terrace insulation on the fifth floor is complete;

-Bathroom insulation work is being done on the fourth floor;

-On the first two floors, the screed has been finished, and the installation of anodized aluminum joinery has been completed.

Continue to follow the construction of your future home, as we will be completing the rough construction work next month!

18.09.2024.